CCWD Hires Engineer For Reach 1 Project

CCWD Hires Engineer For Reach 1 Project

The Calaveras County Water District Board of Directors voted unanimously to hire KASL Consulting Engineers out of Citrus Heights to design the Reach 1 water transmission line project. The firm will design plans for construction crews to remove 24,000 feet of 8-inch steel water pipes beginning on Hunter Dam Road and ending near the entrance to Forest Meadows near Murphys. Those pipes have been in the ground since 1965 and will be replaced with new ductile iron pipes and regulator stations and other equipment will also be replaced. Construction is expected to start in early 2018.

 

Written by This email address is being protected from spambots. You need JavaScript enabled to view it.

Additional information